Assam has the anchor investments. What most projects still need is a clear read on viability, location, incentives, and the supplier disciplines the corridor will expect. We work with two kinds of buyer.
Semiconductor ecosystem engineering is the deliberate coordination of project economics, policy, regional intelligence, supplier capability, quality systems, and institutional relationships, so investments can move from intent to production. In practice, that resolves into four workstreams.
Nitisagar provides ecosystem and market-entry advisory. Specialist process, cleanroom, facilities, and EPC engineering is scoped separately, with appropriately qualified technical partners.
Each product tackles one workstream of the four-part Semiconductor Ecosystem Engineering practice. Use them individually, or as a stack across an advisory engagement.
Eight stages, drawn from our Factory Setup Playbook. Tap each one to see the timeline, authority, and cost. Switch tracks to see the self-declaration exemption the 2020 Act already grants non-polluting units.
Udyam Registration is instant and free. Company or firm registration with the Registrar of Companies takes 7 to 15 days.
An AIDC industrial estate plot is pre-zoned and comes with approach roads, typically allotted in 30 to 90 days. A private plot is cheaper per sqm but needs land-use conversion and can take 120 to 180 days.
Agricultural land cannot be used for manufacturing until it is converted. This is the single biggest source of project delay in Assam.
Building plan approval and Consent to Establish (CTE) from PCB Assam. Construction cannot legally begin without CTE.
Fire Safety NOC, then Factory Licence once your shed and safety infrastructure are in place.
EPF and ESI registration (1 to 3 days each), GST registration (7 to 15 days). All free, all required before you can claim any incentive.
The transformer security deposit surprises most first-time promoters, and the wait routinely runs 3 to 6 months. No grid power, no production.
Consent to Operate (CTO) and Trade Licence. Once both clear, you are producing.
Central schemes like Semicon 2.0 and Assam's own industrial policies, each read from the gazette, not a press summary. Tap a tile for a sourced figure. Where a policy leaves a number to case-by-case negotiation, we say so instead of guessing.
Indicative reading of published policy text, not an eligibility determination.
Read our published analysis, see who controls each stage of the global chip chain, or track live pricing across key semiconductor inputs.
Send us four details: what you plan to make, your indicative investment range, where you are considering, and how far the project has progressed.
In a 30-minute project-fit review, we will identify the first questions to answer, the major information gaps, and whether Nitisagar is the right advisory partner for the next stage. No generic sales presentation. We respond within two business days.