Scheme explainer · Government of India

India Semiconductor Mission

The India Semiconductor Mission (ISM) is the nodal agency under MeitY that runs the Semicon India Programme — India’s central incentive package for chip fabs, packaging, materials, equipment and design. Under Semicon 2.0, notified 31 August 2026, it reimburses 25–40% of eligible capital expenditure across five pillars. Here is what each pillar funds, who qualifies, and how a state subsidy stacks on top.

At a glance Nodal agency ISM Notified 31 August 2026 5 pillars 25–40% capex support

What is the India Semiconductor Mission?

The India Semiconductor Mission (ISM) was set up in 2021 as an independent business division of the Digital India Corporation, under the Ministry of Electronics and Information Technology (MeitY). It is the single nodal agency that appraises applications, disburses incentives and builds the ecosystem for the Semicon India Programme. ISM does not approve projects on its own — it recommends, and the Union Cabinet approves.

The programme was restructured into Semicon 2.0, notified 31 August 2026 (Gazette of India Extraordinary No. 235). Where the original 2021 schemes offered a flat 50% of project cost, Semicon 2.0 organises support into five pillars with segment-specific rates of 25–40% of eligible capex, a design-linked incentive, and an advanced-R&D track. New applicants apply under 2.0.

The Five Pillars of Semicon 2.0

Headline numbers, summarised for scanning. Every figure is read from our gazette-cited scheme data; open the Policy Explorer for the full per-incentive citations, caps and application terms.

Semicon 2.0 pillars: what each funds, the entry threshold, and the capex support rate
Pillar What it funds Entry threshold Support Detail
1Chip design (P-DLI) Fabless / SoC / IP design startups and firms No capital threshold Seed up to Rs 15 Cr, plus 9% of net sales for 5 yrs Citations →
2Machines, materials & test Gases, chemicals, substrates, equipment, test labs From Rs 50 Cr capex 30% of capex (+ PLI on equipment) Citations →
3Fabs & display fabs Silicon, compound, photonics, MEMS and display fabs Rs 500 Cr – Rs 20,000 Cr capex 35–40% of capex Citations →
4ATMP / OSAT packaging Assembly, test, marking & packaging lines Rs 1,000 Cr capex 25% legacy · 35% advanced Citations →
5Advanced R&D Mission-mode semiconductor research Project-based Up to 75% of project cost Citations →

Source: Gazette of India Extraordinary No. 235, notified 31 August 2026, and MeitY’s implementation guidelines for Pillars 2–4 (16 September 2026). Applications run for three years from the guidelines date, online through the ISM portal. Read the gazette ↗

How the Money Actually Reaches You

The acknowledgement clock

Spending before ISM acknowledges your application is never reimbursed. The capex clock starts on the acknowledgement date — not on sanction, and not on the day you break ground.

Pari-passu, via a No-Lien Account

You deposit your own share into a No-Lien Account at an Indian bank first; ISM then releases its pro-rata share. Support is fixed at the approved capex, so overruns — a weaker rupee on imported tools included — are yours.

Three-year lock-in

Promoters hold at least 51% equity through the agreement and for three years after the commercial-operation date, and the unit must stay in production that long. No restructuring in that window without ISM’s nod.

Land and tech licences excluded

Eligible capex covers the building, clean rooms, plant and equipment — even refurbished tools with five years of life left. It does not cover land, its development, technology-transfer fees or R&D running cost.

Stacking a State Subsidy on Top

ISM support is central support. The Semicon 2.0 guidelines confirm a state government’s incentive is “over and above” it, and let the state join the No-Lien Account agreement. In Assam, the Electronics & Semiconductor Policy 2023 offers an additional 40% of the central capex assistance, plus 100% stamp-duty exemption, a power-tariff incentive and payroll assistance.

There is a catch worth knowing before you model it: that 40% top-up is gated on first clearing a central ISM approval, and the state policy text still points at the older Semicon 1.0 schemes. Whether a Semicon 2.0 approval unlocks the Assam top-up — and on which capex base — is not yet settled in the policy text. And because the state share is calculated off the central assistance, a lower 2.0 central rate (25% on legacy packaging, versus 50% under 1.0) shrinks the state top-up too.

This is exactly the kind of stacking question we work on. Ask us how the central and Assam layers fit your project →

Frequently Asked

What is the India Semiconductor Mission?
The India Semiconductor Mission (ISM) is the nodal agency, set up in 2021 as an independent business division of the Digital India Corporation under MeitY, that administers the Government of India’s Semicon India Programme — the central incentive package for building semiconductor fabs, packaging plants, materials, equipment and chip design in India.
What incentives does the India Semiconductor Mission offer?
Under Semicon 2.0 (notified 31 August 2026), ISM reimburses a share of eligible capital expenditure: 40% for a silicon wafer fab, 35% for compound/display fabs and advanced packaging, 25% for legacy ATMP/OSAT packaging, and 30% for machines and materials. Chip-design firms get seed funding up to Rs 15 crore plus a 9% deployment-linked incentive on net sales.
What is the difference between Semicon India 1.0 and 2.0?
Semicon 1.0 (2021) offered a flat 50% of project cost as fiscal support. Semicon 2.0, notified 31 August 2026, restructures the programme into five pillars and sets support at 25–40% of eligible capex depending on segment, with a separate design-incentive and R&D pillar. New applicants apply under 2.0.
Who can apply to the India Semiconductor Mission?
Private or public limited companies owning or licensing production-grade technology, meeting a minimum capex and prior-revenue bar for their segment. The lowest entry bar is Rs 50 crore capex (semiconductor-grade raw materials, gases and chemicals); chip design has no capital threshold at all. ISM appraises applications and the Union Cabinet approves them.
Can a state subsidy be stacked on top of ISM support?
Yes — the Semicon 2.0 guidelines confirm state support is "over and above" central support. Assam’s Electronics & Semiconductor Policy 2023 offers an additional 40% of the central capex assistance, but it is gated on first clearing a central ISM approval and still references the older Semicon 1.0 schemes, so whether a 2.0 approval unlocks it is not yet settled.

Go Deeper

See what your project can actually claim

Two ways in: run the numbers yourself, or have us pressure-test the full central-plus-state stack with you.

How this was built. Every figure on this page is read from the gazette notification (Gazette of India Extraordinary No. 235, 31 August 2026) and MeitY’s implementation guidelines (16 September 2026), via the same curated dataset that powers our Policy Explorer. It is our reading of the published text, for orientation only — not legal, tax or eligibility advice, and not a determination that your project qualifies. Several figures are left to case-by-case appraisal in the scheme itself; those are flagged in the Explorer. Confirm any number with ISM (ism.gov.in) before you rely on it.